Renewable Energy Project Development Business

SAAM Group is currently developing renewable energy projects overseas. As of 31 December 2018, SAAM Group successfully developed 2 biomass power projects in Japan, namely SAAM Oita 01 Biomass Power and SAAM Oita 02 Biomass Power, each with installed capacity of 19.9 MW. Such projects are developed through project companies which are subsidiaries of SJE established in Japan, namely BMP-3 and BMP-4, respectively. Both projects have received Grid Interconnection Approval issued by a private electric company and METI Certification issued by the Ministry of Economy, Trade and Industry (“METI”), Japan. SAAM Group has entered into agreements with clients in specifying the scope of project development and delivery.

Development Process

Analysis and Selection of Potential Project Locations Process
An in-depth analysis into all aspects, in terms of suitability, related to each type of renewable energy project
Grid Interconnection Application Process
Requires interconnection point appropriate to the generation capacity of the proj
FiT Application Process
Involves the preparation of a complete list of supporting documents as required by each country’s government agency
Business Partner Negotiation Process
Negotiation with all partners to conclude terms and conditions appropriate to each type of renewable energy project’s operations in each country as required by financial institutions
Credit Facility Application Process
Preparation of a complete range of financial information, project documents, and agreement documents, as well as negotiation regarding credit terms with financial institutions
Construction and Other Permits Application Process
Involves the preparation of supporting documents, explanation, and negotiation with government agencies as required by each country

Projects

SAAM Oita 01 Biomass Power
  • LocatedOita City, Oita Prefecture
  • Land Area70,000 square meters
  • Operating Under BMP-3
  • Installed Capacity 19.90 MB
  • FiT JPY 24 per kWh
  • Offtaker Kyushu Electric Power
  • Feedstock/strong> Wood Pellets and PKS

SAAM Oita 02 Biomass Power
  • LocatedOita City, Oita Prefecture
  • Land Area70,000 square meters
  • Operating Under BMP-3
  • Installed Capacity 19.90 MB
  • FiT JPY 24 per kWh
  • Offtaker Kyushu Electric Power
  • Feedstock/strong> Wood Pellets and PKS